Palmetto LightReach Newsfeed
New feature

[LIVE] LightReach Installer Support Available Through WhatsApp

Calvin avatar
Shared by Calvin • October 27, 2025

The Headline: LightReach Installer Support can now be reached via WhatsApp Messenger.

The Details: Similar to our existing SMS option, WhatsApp offers an additional avenue for partners to reach PLR support- especially for those in field.

How to Contact: Message "INSTALLER" into 980-272-0985 on WhatsApp

Event

Halloween Limited Hours

Mare- avatar
Shared by Mare- • October 24, 2025

PLR Support will be available with adjusted hours on Friday 10/31 & Saturday 11/1. Normal hours will resume on Sunday 11/2.

Sales & Underwriting Support: 11am-4pm EST

Operations (QC) Support: 11am-4ET

Market Update

[Advance Preview] California Interconnection Application Submission - 11/1

Anita-PLR avatar
Shared by Anita-PLR • October 24, 2025

Update:

Beginning November 1, 2025, California residential solar Interconnection Application submissions must include a new Solar Energy System Supporting Information document. The 7-page document, also referred to as the CSLB Disclosure Document, requires a 1-year energy savings estimate with standardized inputs and assumptions for solar or solar+storage.

Palmetto LightReach will begin requiring a copy of the completed Solar Energy System Supporting Information document at Milestone 1 on submissions beginning November 1, 2025.

Installation partners are expected to complete the savings estimate, collect the hourly usage history, all remaining fields, and provide a copy to the homeowner. Template here.

Policy Update

Battery Settings & Operational Modes

Calvin avatar
Shared by Calvin • October 16, 2025

LightReach has released a guide for Battery Settings and Operational Modes Guide. Installers must ensure that all customer battery settings accurately reflect the customer’s contract type, utility rate plan, and intended operation. Proper configuration is critical for system performance and compliance.


Current Setting Requirements:

Effective September 15, 2025:

  • Customers with Full Services (Backup) Batteries must have:
  • A 20% minimum Battery Reserve level.
  • ‘Storm Guard’ settings enabled.

Upcoming Changes – Q1 2026

California (CA):

  • Time-of-Use (TOU) modes will become mandatory for Arbitrage contracts only.
  • The utility's NEM 3 rate plan must be selected.
  • Installers should begin preparing now for this requirement.

Arizona (AZ):

  • Self-Consumption mode is the recommended setting.
  • TOU mode is also acceptable, however, is a risk if buy and sell rates are not accurate.

All Other States and Non-Arbitrage Contracts:

  • Operational modes remain recommendations; please refer to the guide for details.

Next Steps

  • All installers are encouraged to use this information to educate both their teams and customers on optimizing battery system performance. HERE
  • LightReach will continue to provide training and resources to support this transition.

Hardware & AVL
Market Update

Solar AVL, Hardware, & FEOC Guidance

Andrew avatar
Shared by Andrew • October 09, 2025

The Headline: We have published our initial FEOC guidance to partners and consolidated our AVL and other hardware-related articles into one single guide.

The Details: This central article features a few notable updates:

  1. Provides initial October FEOC guidance for partners, which will evolve.
  2. Consolidates multiple knowledge base articles into one (including our Solar AVL & Domestic Content Articles)
  3. Solar AVL Updates, including the addition of some modules (Mission, REC) and removal of others (URE, Panasonic).

The Horizon: FEOC guidance will evolve. Partners should bookmark this newsfeed (news.golightreach.com) and the above article for future updates.

Hardware & AVL

Battery and Hardware Updates

Calvin avatar
Shared by Calvin • September 26, 2025

Battery Update:

Contracts with Backup Batteries require:

  • 20% minimum backup reserve
  • Storm Guard enabled

These settings are already standard in most installations.

SolarEdge Batteries

  • Battery Reserve and Weather Guard can only be set via SetApp.
  • Starting 10/13/25: commissioning photos required with all M2 submissions.
  • Until then, M1 projects will have a Stip flag requiring screenshots at M2.

QCells Combiner Requirements:

Follow manufacturer rules: [Full Article HERE]

  • Do Not Drill zones must be respected.
  • Conduit entry allowed only at the bottom.

Noncompliance will require a combiner replacement before M1 approval.

Market Update
Milestone Update

[LIVE] Temporary Change to NJ ADI Submission Requirements

Anita-PLR avatar
Shared by Anita-PLR • September 26, 2025

The Background: New Jersey has temporarily updated it’s ADI guidelines in an effort to help more consumers get solar installed before the end of 2025.

The Change: New Jersey’s ADI Conditional Approval, a submission requirement for Installation (M1), is temporarily changing to Proof of Submittal, rather than the approval itself.

  • Changing from: Must submit formal approval
  • Changing to: Temporarily changing to Proof of Submission only.

The Details: We will accept any reasonable format of Proof of Submission:

  • Recommended: Screenshot of ADI portal submission
  • What we’re looking for: Reasonable proof of submission clearly identifying the customer account

The Fine Print:

  • When: Effective immediately, for all new installation submissions from Friday 9/26/26 (until further notice)
  • Big Picture: This change is temporary, and PLR will revisit the requirement later in 2025.

Market Update

[LIVE] Upcoming Nevada Compliance Changes

Anita-PLR avatar
Shared by Anita-PLR • September 26, 2025

The Update: Beginning October 1, Palmetto LightReach will be making the appropriate adjustments to our consumer PPA agreements, consumer protection standards, and partner milestone requirements as part of Compliance with NV Senate Bill's 440 & 379. These consumer protection focused changes build on Senate Bill 293's requirements that were implemented across the market last year. We will communicate and post additional details for all those active and compliant Nevada installation partners next week and thank you for your patience and dialogue as we've worked to implement these changes in the best interests of consumers and partners under the new laws.

The Impact: All changes to Partner processes will be weaved into standard practices and milestone deliverables that exist today.

Hardware & AVL

[Live] Solar AVL Additions

Brandon avatar
Shared by Brandon • September 26, 2025

The Update: Three new updates have been made to our Solar Program AVL, from 9/26/25.

  • Inverter: Solaredge SKU USE11400H-USSKBEZ8 added to AVL.
  • Panel: Wattages expanded on the SEG Yukon N SEG-xxx-BTD-BG up to 445W
  • Panel: Trina Vertex S+ TSM-xxxNEG9R.25 (430-455W) added to AVL.

The Fine Print: These AVL additions are eligible for new installations from 9/26/25.

Hardware & AVL

Hardware Update

Alvin avatar
Shared by Alvin • September 19, 2025

Two new articles have been updated and published to provide additional installation guidance and documentation:

  1. QCells AC Module – Design, Install & Commissioning
    Installers should reference the technical installation documents.
    [Full Article HERE]
  2. Domestic Content – (M1) Submittal & Photo Requirements
    This article compiles module manufacturer details, now including Elin/Sirius, Qcells, and Silfab solar modules, along with photos.
    [Full Article HERE]